Question #: 70
Topic #: 7

A.

Cost Breakdown Structure (CBS) shows costs assigned to:


B.

individual work packages using the Work Breakdown Structure (WBS).


C.

individual resources using the Work Breakdown Structure (WBS).


D.

individual resources using the Responsibility Assignment Matrix (RAM).


E.

individual deliverables using the Responsibility Assignment Matrix (RAM)