APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 42 Topic 4 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 42 Topic 4 Discussion

APM-PFQ Exam Topic 4 Question 42 Discussion:
Question #: 42
Topic #: 4

Which structure shows the reporting relationships and communications channels for a project?


A.

Work Breakdown Structure.


B.

Organisational Breakdown Structure.


C.

Product Breakdown Structure.


D.

Responsibility assignment structure.