Question #: 96
Topic #: 9

The main aim of a project risk management process should be to:


A.

identify project risks and then manage them appropriately.


B.

identify all project risks and transfer them immediately.


C.

identify all the things that are threats or opportunities on a project.


D.

satisfy the organisation's project management process.