APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 97 Topic 9 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 97 Topic 9 Discussion

APM-PFQ Exam Topic 9 Question 97 Discussion:
Question #: 97
Topic #: 9

What information would you not expect to see in a project management plan?


A.

Quality management plan.


B.

Financial feasibility analysis.


C.

Risk management plan.


D.

Details of scope.