APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 92 Topic 9 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 92 Topic 9 Discussion

APM-PFQ Exam Topic 9 Question 92 Discussion:
Question #: 92
Topic #: 9

The project management plan is best described as a reference document that confirms:


A.

the project completion date as agreed between the project sponsor, other stakeholders and the project manager.


B.

the agreement between the project sponsor, other stakeholders and the project manager.


C.

the key project milestones as agreed between the project sponsor, other stakeholders and the project manager.


D.

the project start date as agreed between the project sponsor, other stakeholders and the project manager