APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 38 Topic 3 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 38 Topic 3 Discussion

APM-PFQ Exam Topic 3 Question 38 Discussion:
Question #: 38
Topic #: 3

To develop and establish a proper communication plan within a project, the project manager needsto consider which type of analysis?


A.

Budget.


B.

Stakeholder.


C.

Resource.


D.

Schedule


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer: