APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 31 Topic 3 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 31 Topic 3 Discussion

APM-PFQ Exam Topic 3 Question 31 Discussion:
Question #: 31
Topic #: 3

How is the deployment baseline used throughout the project?


A.

Progress monitoring and implementation of change control.


B.

Benefits realisation.


C.

Identify options for deployment.


D.

Prepare users for delivery of the output into operation.