Which of the following would be considered most important when carrying out A. detailed evaluation of a change?
Impact of change on baseline, risks and business case.
The number of extra people required to deliver the change.
How the change will be reported when it is implemented into the project.
The configuration requirements Of the change when implemented into the project,