Questions # 51:

A building manager is comparing the operating cost of the existing boiler to the purchase and operation of a new and more efficient boiler. The building manager discovers that although the upfront cost is significant, purchasing the new boiler would drastically decrease the cost of running and operating the system. This exercise is called

Options:

A.

life-cycle costing


B.

value engineering


C.

integrated design


D.

life-cycle assessment


Expert Solution
Questions # 52:

The amount of landfill-destined waste generated during project construction can be reduced by requiring the general contractor to

Options:

A.

burn paper and cardboard materials on-site


B.

use contractor vehicles to disperse waste materials to multiple disposal sites within the project region


C.

follow requirements for using dimensional construction materials, prefabrication or material efficient framing


D.

take advantage of municipal waste pick-up to reduce the weight of the project's construction material scraps


Expert Solution
Questions # 53:

Which strategy promotes sustainable purchasing during construction?

Options:

A.

Specify green electronic equipment


B.

Develop a construction purchasing policy


C.

Reduce regional materials expense by 10%


D.

Implement an erosion and sedimentation plan


Expert Solution
Questions # 54:

The LEED Pilot credit library plays an important role in the continuous evolution of LEED by

Options:

A.

developing new credits for U.S. projects only


B.

achieving the next threshold for exemplary performance


C.

limiting the number of times that a credit category appears in the rating system


D.

providing U.S. Green Building Council (USGBC) with feedback on achievability of proposed credits


Expert Solution
Questions # 55:

Which of the fallowing projects is eligible for LEED for Building Operations and Maintenance; Existing Buildings?

Options:

A.

A two-story LEED certified apartment building


B.

A park adjacent to a LEED certified building


C.

An existing single-family home that is LEED certified


D.

An existing LEED certified building located on a college campus


Expert Solution
Questions # 56:

Which of the following contribute to the triple bottom line?

Options:

A.

Global security


B.

Social responsibility


C.

Project balance sheet


D.

Green metrics and verification


Expert Solution
Questions # 57:

Which of the following has the highest energy consumption in a typical U.S. office building?

Options:

A.

Lighting


B.

Cooling


C.

Space Heating


D.

Water Heating


Expert Solution
Questions # 58:

Which of the following Is a source of green power?

Options:

A.

Clean coal


B.

Wind turbine


C.

Nuclear fission


D.

Natural gas captured by hydraulic fracturing


Expert Solution
Questions # 59:

Which of the following team members should participate in the initial evaluation to determine which level of LEED certification to target?

Options:

A.

Owner


B.

Zoning Official


C.

Project Safety Officer


D.

Green Business Certification Inc. (GBCI) Certification Reviewer


Expert Solution
Questions # 60:

Which of the following approaches refers to the identification and quantification of environmental effects throughout the life of the materials andproducts used in a project as well as the project itself?

Options:

A.

Commissioning


B.

Integrative process


C.

Life-cycle costing (LCC)


D.

Life-cycle assessment (LCA)


Expert Solution