Questions # 151:

Monitor and control project work is a process of which of the following knowledge areas?

Options:

A.

Project risk management


B.

Project scope management


C.

Project time management


D.

Project integration management


Expert Solution
Questions # 152:

The degree of risk shared between the buyer and seller is determined by the:

Options:

A.

contract type.


B.

sponsors.


C.

project manager.


D.

stakeholders.


Expert Solution
Questions # 153:

The Project Integration Management knowledge area includes which of the following set of processes?

Options:

A.

Develop Project Charter, Direct and Manage Project Execution, Perform Integrated Change Control


B.

Define Project Scope, Create WBS, Close Project or Phase


C.

Develop Project Charter, Develop Human Resource Plan, Estimate Costs


D.

Identify Stakeholders, Plan Communications, Develop Project Management Plan


Expert Solution
Questions # 154:

Which of the following must be taken into account for every process, even if they are not explicitly listed as inputs in the process specifications?

Options:

A.

Organizational processes and procedures and enterprise environmental factors


B.

Organizational processes and procedures and corporate knowledge base


C.

Organizational process assets and enterprise environmental factors


D.

Corporate knowledge base and enterprise environmental factors


Expert Solution
Questions # 155:

Which of the following is one of the key components of the basic communications model?

Options:

A.

Push


B.

Decode


C.

Pull


D.

Duration


Expert Solution
Questions # 156:

Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your office works different hours than all the other offices. Additionally, not all of the resources in your building are available at the same times during the day. Three of the 12 team members work swing shift hours. You use tools like web conferencing and email to distribute information to the team.

Which of the following is true?

Options:

A.

This question describes resource availability from the Develop Project Team process and information distribution methods from the Information Distribution process.


B.

This question describes the staffing management plan from the Acquire Project Team process and communication skills from the Information Distribution process.


C.

This question describes project staff assignments from the Develop Project Team process and communication skills from the Information Distribution process.


D.

This question describes virtual teams from the Acquire Project Team process and information distribution methods from the Information Distribution process.


Expert Solution
Questions # 157:

You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away.

Which of the following statements is true?

Options:

A.

This project ended due to integration because it was completed and accepted.


B.

This project ended due to extinction because it was completed and accepted.


C.

This project ended due to integration because it was completed and accepted and the project manager moved on to a new project.


D.

This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films.


Expert Solution
Questions # 158:

Which of the following is a technique for Identify Risks?

Options:

A.

Risk categorization


B.

SWOT analysis


C.

Risk register categorization


D.

Risk probability and impact assessment


Expert Solution
Questions # 159:

You are a project manager of ABC organization. You are estimating the project in initiation phase.

What level of accuracy you can expect?

Options:

A.

-75 percent to +75 percent


B.

-25 percent to +25 percent


C.

-50 percent to +50 percent


D.

-50 percent to +100 percent


Expert Solution
Questions # 160:

Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

Options:

A.

Project sponsor and project manager


B.

Project sponsor and functional manager


C.

Project manager and project team


D.

Project team and functional manager


Expert Solution
Questions # 161:

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

Options:

A.

Schedule Control


B.

Activity Definition


C.

Schedule Development


D.

Activity Resource Estimating


Expert Solution
Questions # 162:

If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?

Options:

A.

0.66


B.

0.8


C.

1.25


D.

1.5


Expert Solution
Questions # 163:

Constraints do not include:

Options:

A.

Expected staff assignments


B.

Collective bargaining


C.

Organizational structure of the performing organization


D.

Impacts of weather


Expert Solution
Questions # 164:

To complete performance index (TCPI) is represented by which of the following?

Options:

A.

BAC - EV/BAC - AC


B.

A measure of the value of work completed compared to the actual cost or progress


C.

A measure of progress achieved compared to progress planned


D.

AC + (BAC - EV)


Expert Solution
Questions # 165:

Which of the following statements is in agreement with McGregor's concepts concerning Theory X and Theory Y managers?

Options:

A.

All of the other alternatives apply


B.

Theory X managers tend to be autocratic whereas Theory Y managers are more likely to delegate responsibility


C.

Both 1) Theory X managers view subordinates as being lazy, irresponsible, and resistant to change, and 2) Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility


D.

Theory Y managers view subordinates as being imaginative, creative, and willing to accept responsibility


E.

Theory X managers view subordinates as being lazy, irresponsible, and resistant to change


Expert Solution