Question #: 159
Topic #: 16

You are a project manager of ABC organization. You are estimating the project in initiation phase.

What level of accuracy you can expect?


A.

-75 percent to +75 percent


B.

-25 percent to +25 percent


C.

-50 percent to +50 percent


D.

-50 percent to +100 percent