Questions # 181:

Total funding requirements and periodic funding requirements are derived from:

Options:

A.

funding limit reconciliation


B.

scope baseline


C.

activity cost estimates.


D.

cost baseline.


Expert Solution
Questions # 182:

The basic elements of communication include:

Options:

A.

Reading, writing and listening


B.

Communicator, encoding, message, medium, decoding, receiver, and feedback


C.

All of the other alternatives apply


D.

Clarity of speech and good listening habits


E.

Listening, talking and sign language.


Expert Solution
Questions # 183:

If two events cannot both occur in a single trial, they are:

Options:

A.

False events.


B.

Mutually exclusive.


C.

Statistically independent.


D.

Just-in-time.


Expert Solution
Questions # 184:

If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following?

Options:

A.

The activity will take from 464 to 536 days.


B.

The activity will take from 494 to 506 days.


C.

The activity will take from 476 to 524 days.


D.

The activity will take from 488 to 512 days.


Expert Solution
Questions # 185:

You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525.

What is VAC?

Options:

A.

25


B.

30


C.

20


D.

70


Expert Solution
Questions # 186:

Which is an input to the Scope Verification Process?

Options:

A.

Performance report


B.

Work breakdown structure


C.

Requested changes


D.

Project scope statement


Expert Solution
Questions # 187:

Which of the following is an output of Define Scope?

Options:

A.

Project document updates


B.

Project management plan


C.

Scope baseline


D.

Product analysis


Expert Solution