BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 186 Topic 19 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 186 Topic 19 Discussion

ISEB-PM1 Exam Topic 19 Question 186 Discussion:
Question #: 186
Topic #: 19

Which is an input to the Scope Verification Process?


A.

Performance report


B.

Work breakdown structure


C.

Requested changes


D.

Project scope statement