Questions # 61:

Which of the following is involved in the initiation process group?

Options:

A.

Develop Project Management Plan


B.

Identify Stakeholders


C.

Plan Communications


D.

Collect Requirements


Expert Solution
Questions # 62:

Which of the following is an example of a tool used in Plan Quality?

Options:

A.

Fishbone diagram


B.

Quality audit


C.

Cause and effect diagram


D.

Benchmarking


Expert Solution
Questions # 63:

The inputs of the Performance Reporting process include all of the following except for which one?

Options:

A.

Performance reviews


B.

Work performance information


C.

Forecasted completion


D.

Performance measurements


Expert Solution
Questions # 64:

A clear definition of the user's needs serves as the direct basis for the:

Options:

A.

Selection of personnel.


B.

Termination decision.


C.

Work breakdown structure.


D.

Functional requirements.


E.

Project cost estimate.


Expert Solution
Questions # 65:

Which describes how cost variances will be managed?

Options:

A.

Cost management plan


B.

Cost baseline


C.

Cost estimate


D.

Chart of accounts


Expert Solution
Questions # 66:

The scope management plan is a subsidiary of which project document?

Options:

A.

Schedule management plan


B.

Project management plan


C.

Quality management plan


D.

Resource management plan


Expert Solution
Questions # 67:

How is the process of collecting requirements defined?

Options:

A.

Defining and documenting project sponsors' needs to meet the project objectives


B.

Defining and documenting stakeholders' needs to meet the project objectives


C.

Defining and documenting the project teams' needs to meet the project objectives


D.

Defining and documenting the project needs to meet the project objectives


Expert Solution
Questions # 68:

The scope of a project can be expected to change if:

Options:

A.

The project manager must provide cost estimates without having a design concept.


B.

All of the other alternatives apply are possible based upon the situation.


C.

The project manager is assigned after the project is defined, and the cost and schedule are approved.


D.

A clear objective is not provided.


E.

Oversimplification (underestimating) of the nature of the work occurs.


Expert Solution
Questions # 69:

Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and techniques of what process?

Options:

A.

Perform Quality Control


B.

Perform Quality Assurance


C.

Quality Planning


D.

Performance Reporting


Expert Solution
Questions # 70:

In which domain of project management would a Pareto chart provide useful information?

Options:

A.

Scope Management


B.

Time Management


C.

Communications Management


D.

Quality Management


Expert Solution
Questions # 71:

What causes replanning of the project scope?

Options:

A.

Requested changes


B.

Project scope statement changes


C.

Variance analysis


D.

Approved change requests


Expert Solution
Questions # 72:

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit


B.

Share


C.

Enhance


D.

Transfer


Expert Solution
Questions # 73:

The critical path in a schedule network is the path that:

Options:

A.

Takes the longest time to complete


B.

Allows some flexibility in scheduling a start time.


C.

Is not affected by schedule slippage


D.

Must be done before any other tasks


E.

All of the other alternatives apply.


Expert Solution
Questions # 74:

The highest degrees of project risk and uncertainty are associated with the following phase of the project:

Options:

A.

Both 1) conceptual, and 2) post project evaluation


B.

cut-over


C.

conceptual


D.

execution


E.

post project evaluation


Expert Solution
Questions # 75:

Define Activities and Estimate Activity Resources are processes in which project management knowledge area?

Options:

A.

Time management


B.

Cost management


C.

Scope management


D.

Human resources management


Expert Solution
Viewing page 5 out of 13 pages
Viewing questions 61-75 out of questions