ISEB-PM1 Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?


A.

Exploit


B.

Share


C.

Enhance


D.

Transfer