BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 73 Topic 8 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 73 Topic 8 Discussion

ISEB-PM1 Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

The critical path in a schedule network is the path that:


A.

Takes the longest time to complete


B.

Allows some flexibility in scheduling a start time.


C.

Is not affected by schedule slippage


D.

Must be done before any other tasks


E.

All of the other alternatives apply.


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.