ISEB-PM1 Exam Topic 7 Question 64 Discussion:
Question #: 64
Topic #: 7

A clear definition of the user's needs serves as the direct basis for the:


A.

Selection of personnel.


B.

Termination decision.


C.

Work breakdown structure.


D.

Functional requirements.


E.

Project cost estimate.