ISEB-PM1 Exam Topic 7 Question 61 Discussion:
Question #: 61
Topic #: 7

Which of the following is involved in the initiation process group?


A.

Develop Project Management Plan


B.

Identify Stakeholders


C.

Plan Communications


D.

Collect Requirements