Questions # 76:

Which of the following will be required to perform simu-lation for schedule risk analysis?

Options:

A.

Activity list and activity attributes


B.

Schedule network diagram and duration estimates


C.

Schedule data and activity resource requirements


D.

Milestone list and resource breakdown structure


Expert Solution
Questions # 77:

A contract management plan is a subsidiary of what other type of plan?

Options:

A.

Resource plan


B.

Project management plan


C.

Cost control plan


D.

Expected monetary value plan


Expert Solution
Questions # 78:

Which activity is an input to the select seller’s process?

Options:

A.

Organizational process assets


B.

Resource availability


C.

Change control process


D.

Team performance assessment


Expert Solution
Questions # 79:

Parametric Estimating is done as a part of which process:

Options:

A.

Estimate Activity Durations


B.

Sequence Activities


C.

Develop Schedule


D.

Estimate Activity Resources


Expert Solution
Questions # 80:

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition


B.

Benchmarking


C.

Inspection


D.

Checklist analysis


Expert Solution
Questions # 81:

Which of the following is an input to Develop Human Resource Plan?

Options:

A.

Team performance assessment


B.

Roles and responsibilities


C.

Staffing management plan


D.

Enterprise environmental factors


Expert Solution
Questions # 82:

Which tool is used to develop technical details within the project management plan?

Options:

A.

Expert Judgment


B.

Project Management Methodology


C.

Project Management Information


D.

Project Selection Methods


Expert Solution
Questions # 83:

What should be covered in an implementation when the change is approved?

Options:

A.

Functional requirement


B.

Status report


C.

Customer need


D.

Defect repair


Expert Solution
Questions # 84:

A team member from research and development tells you that her work is too creative to provide you with a fixed single estimate for the activity. You both decide to use the average labor hours per installation from past projects to predict the future.

This is an example of which of the following?

Options:

A.

Parametric estimating


B.

Three-point estimating


C.

Analogous estimating


D.

Monte Carlo analysis


Expert Solution
Questions # 85:

A work breakdown structure is most useful for:

Options:

A.

determining potential delays


B.

developing a cost estimate


C.

scheduling the start of tasks


D.

identifying individual tasks for a project


E.

A and C


Expert Solution
Questions # 86:

A work authorization system can be used to:

Options:

A.

Manage who does each activity.


B.

Manage when and in what sequence work is done.


C.

Manage when each activity is done.


D.

Manage who does each activity and when it is done.


Expert Solution
Questions # 87:

Which of the following helps a project manager determine possible causes of problems on a project?

Options:

A.

The 50/50 rule


B.

A fishbone diagram


C.

A control chart


D.

A Pareto chart


Expert Solution
Questions # 88:

What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?

Options:

A.

Idle resources


B.

Negative float


C.

Lots of free float


D.

Positive float


Expert Solution
Questions # 89:

The approval of which of the following indicates formal initiation of the project?

Options:

A.

Procurement management plan


B.

Project management plan


C.

Project scope document


D.

Project charter


Expert Solution
Questions # 90:

You are about to begin negotiations with people from another country.

Which of the following should provide guidance on what business practices are allowed and not allowed?

Options:

A.

The company code of conduct


B.

The project charter


C.

The scope management plan


D.

The negotiation plan


Expert Solution
Viewing page 6 out of 13 pages