New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 86 Topic 9 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 86 Topic 9 Discussion

ISEB-PM1 Exam Topic 9 Question 86 Discussion:
Question #: 86
Topic #: 9

A work authorization system can be used to:


A.

Manage who does each activity.


B.

Manage when and in what sequence work is done.


C.

Manage when each activity is done.


D.

Manage who does each activity and when it is done.


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.