BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 76 Topic 8 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 76 Topic 8 Discussion

ISEB-PM1 Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

Which of the following will be required to perform simu-lation for schedule risk analysis?


A.

Activity list and activity attributes


B.

Schedule network diagram and duration estimates


C.

Schedule data and activity resource requirements


D.

Milestone list and resource breakdown structure


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.