ISEB-PM1 Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

You are about to begin negotiations with people from another country.

Which of the following should provide guidance on what business practices are allowed and not allowed?


A.

The company code of conduct


B.

The project charter


C.

The scope management plan


D.

The negotiation plan