ISEB-PM1 Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?


A.

Decomposition


B.

Benchmarking


C.

Inspection


D.

Checklist analysis