BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 80 Topic 9 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 80 Topic 9 Discussion

ISEB-PM1 Exam Topic 9 Question 80 Discussion:
Question #: 80
Topic #: 9

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?


A.

Decomposition


B.

Benchmarking


C.

Inspection


D.

Checklist analysis


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.