BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 162 Topic 17 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 162 Topic 17 Discussion

ISEB-PM1 Exam Topic 17 Question 162 Discussion:
Question #: 162
Topic #: 17

If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is $1500, what would be the cost performance index (CPI)?


A.

0.66


B.

0.8


C.

1.25


D.

1.5


Get Premium ISEB-PM1 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.