Question #: 157
Topic #: 16

You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away.

Which of the following statements is true?


A.

This project ended due to integration because it was completed and accepted.


B.

This project ended due to extinction because it was completed and accepted.


C.

This project ended due to integration because it was completed and accepted and the project manager moved on to a new project.


D.

This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films.