During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.
Is this an appropriate application of the ‘capture issues and risks’ activity, and why?
The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.
Is this an appropriate approach to leading a successful team, and why?
During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.
Which role should lead this business-related ongoing direction?
At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.
Is this an appropriate application of the progress practice, and why?
During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.
Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?
The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.
Does this represent an appropriate application of the ‘business case’ practice, and why?