Questions # 11:

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?

Options:

A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue


B.

Yes, because the project manager may dismiss an informally raised concern without further investigation


C.

No, because the project manager should assess an informally raised concern before deciding what action to take


D.

No, because the team manager should report the concern only in the next scheduled checkpoint report


Expert Solution
Questions # 12:

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?

Options:

A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project


B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package


C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options


D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working


Expert Solution
Questions # 13:

During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.

Which role should lead this business-related ongoing direction?

Options:

A.

Project executive


B.

Project manager


C.

Project assurance


D.

Senior user


Expert Solution
Questions # 14:

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?

Options:

A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board


B.

Yes, because the project board should collect and review work-package progress directly from each delivery team


C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances


D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages


Expert Solution
Questions # 15:

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?

Options:

A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion


B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process


C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work


D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio


Expert Solution
Questions # 16:

The Louistown City Council operates a well-established and standardized project management framework that includes a defined procedure for developing business cases. For the LouisShopping Project, a ‘strategic business case’ was included in the project brief submitted to the project board at the conclusion of the ‘starting up a project’ process. The project has now entered the ‘initiating a project’ process, during which the full business case is being built upon the strategic business case, which was itself derived from the Council’s five-year strategic plan for the ‘Louistown is Open for Business’ portfolio.

Does this represent an appropriate application of the ‘business case’ practice, and why?

Options:

A.

Yes, because developing the business case from multiple perspectives – strategic, economic, and commercial – ensures a comprehensive and robust justification for the project investment


B.

Yes, because the project should align its approach to business case development with the City Council’s established procedure, which serves as the equivalent of PRINCE2’s recommended business case lifecycle


C.

No, because the full business case should be developed from an outline business case prepared during the ‘starting up a project’ process, and using a ‘strategic business case’ instead is not compliant with the method


D.

No, because responsibility for developing the full business case for each project in the portfolio lies with the portfolio office, not the project team