PRINCE2-7-Practitioner Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

During stage 3, the foundations team manager tells the project manager that the completed foundations may have changed rainwater flow onto a neighbouring property. The project manager notes the concern in the project log but dismisses it without assessment and instructs the team to continue because the design has planning approval.

Is this an appropriate application of the ‘capture issues and risks’ activity, and why?


A.

Yes, because recording the concern in the project log is sufficient before allowing delivery to continue


B.

Yes, because the project manager may dismiss an informally raised concern without further investigation


C.

No, because the project manager should assess an informally raised concern before deciding what action to take


D.

No, because the team manager should report the concern only in the next scheduled checkpoint report