Month End Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 10 Topic 2 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 10 Topic 2 Discussion

PRINCE2-7-Practitioner Exam Topic 2 Question 10 Discussion:
Question #: 10
Topic #: 2

Before a BuildyBrick subcontractor begins testing the utilities and systems, the proposed team plan and the commitment to deliver the testing work package must be agreed.

Which role agrees to carry out the work package in the ‘managing product delivery’ process?


A.

Project manager


B.

Team manager


C.

Senior supplier


D.

Project support


Get Premium PRINCE2-7-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.