Month End Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 9 Topic 1 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 9 Topic 1 Discussion

PRINCE2-7-Practitioner Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

In stage 4, the Heritage Director delegates a review of the inspection arrangements to the Heritage Manager. The Heritage Manager will work with the BuildyBrick CEO and the project manager, then report whether the planned inspections will provide adequate assurance about impacts on historic buildings.

Is this an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?


A.

Yes, because the principle requires that communication channels between all internal and external project team members remain open and transparent at all times


B.

Yes, because the Heritage Manager needs a clear understanding of what the Heritage Director requires of them and of what they may reasonably expect from the other parties involved


C.

No, because it is the project manager’s responsibility to specify how inspections of historically significant buildings should be planned and executed


D.

No, because the Heritage Director, as senior user, should personally conduct the assurance review of the inspection plans rather than delegating to the Heritage Manager


Get Premium PRINCE2-7-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.