Month End Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 12 Topic 2 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 12 Topic 2 Discussion

PRINCE2-7-Practitioner Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

The stage 4 inspections cannot start because a geological survey is late. Although the survey team is generally qualified, it lacks a specific technical capability needed to complete the survey. Without first assessing the gap, the project manager recommends replacing the entire team with a subcontractor, which would cause a significant further delay.

Is this an appropriate approach to leading a successful team, and why?


A.

Yes, because bringing in a replacement subcontractor with the necessary technical skills will enable stage 4 activities to resume and reduce the risk of further delays to the overall project


B.

Yes, because the project manager has the authority to source a subcontractor when an existing team member lacks the technical competence required for their assigned work package


C.

No, because before recommending full team replacement the project manager should first seek to understand the nature of the competency gap and explore support options


D.

No, because the project manager and the survey team manager jointly developed and agreed the terms of the work package, and replacing the team contradicts the co-created ways of working


Get Premium PRINCE2-7-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.