PRINCE2-7-Practitioner Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

During stage 4, the business identifies a need for additional funding to extend LouisShopping advertising beyond project closure so that more businesses are attracted to Louistown. The project board must communicate the business need and resulting direction to the project team.

Which role should lead this business-related ongoing direction?


A.

Project executive


B.

Project manager


C.

Project assurance


D.

Senior user