Month End Sale Special Limited Time 75% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 14 Topic 2 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 14 Topic 2 Discussion

PRINCE2-7-Practitioner Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

At the start of stage 3, the project board inserts detailed recycling tolerances directly into each work package without the project manager agreeing the delegated targets with the relevant team managers.

Is this an appropriate application of the progress practice, and why?


A.

Yes, because team managers generally need to comply with sustainability metrics set directly by the project board


B.

Yes, because the project board should collect and review work-package progress directly from each delivery team


C.

No, because the project manager should authorize the work packages and agree the delegated sustainability tolerances


D.

No, because sustainability tolerances should be recorded only at project level rather than delegated through work packages


Get Premium PRINCE2-7-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.