PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 15 Topic 2 Discussion

PRINCE2 Project Management Practitioner (Version 7) PRINCE2-7-Practitioner Question # 15 Topic 2 Discussion

PRINCE2-7-Practitioner Exam Topic 2 Question 15 Discussion:
Question #: 15
Topic #: 2

During the ‘starting up a project’ process, the Business Opportunities Director appoints the Regeneration Manager as project manager and states that the portfolio’s standard role description will apply without discussion. The Regeneration Manager asks to confirm the responsibilities, but the Director refuses because the project is urgent.

Is the refusal an appropriate application of the ‘define roles, responsibilities and relationships’ principle, and why?


A.

Yes, because standardized portfolio role descriptions give every project manager a consistent and well-understood baseline of responsibilities, removing the need for individual discussion


B.

Yes, because it is the project executive’s responsibility to appoint the project manager and establish their responsibilities as part of the ‘starting up a project’ process


C.

No, because each project manager must have a clear understanding of their own individual responsibilities and formally accept those responsibilities before commencing project work


D.

No, because it is the portfolio manager’s role, rather than the project executive’s, to define the project manager’s responsibilities for projects within the portfolio