Pass the PMI PMI Professional in Business Analysis PMI-PBA Questions and answers with CertsForce

Viewing page 4 out of 6 pages
Viewing questions 31-40 out of questions
Questions # 31:

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.


B.

quality control by determining the control charts and the run charts.


C.

quality assurance by structuring the quality audits.


D.

controlling the effects between the quality functions.


Expert Solution
Questions # 32:

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Options:

A.

vote on the product's highest-value business needs.


B.

negotiate to best meet each department's objectives.


C.

collaborate on a product scope that aligns with the company’s objectives.


D.

delegate the decision to be made by the product sponsor.


Expert Solution
Questions # 33:

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

Options:

A.

prepare a test procedure for the product to discuss at the requirements review.


B.

start designing the product to impress the customer with the amount of progress achieved early in the project.


C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.


D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.


Expert Solution
Questions # 34:

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming


B.

Interviewing


C.

Prototyping


D.

Surveying


Expert Solution
Questions # 35:

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline


B.

How requirement changes will be implemented


C.

How requirement changes will impact the validation plan


D.

How requirement changes will be communicated


Expert Solution
Questions # 36:

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

Options:

A.

Distribution of project changes


B.

Requirements status during the project development cycle


C.

Number of requirements approved vs. number of requirements rejected


D.

Number of requirements tested and approved


Expert Solution
Questions # 37:

A project that was going well for the last few months has encountered a situation—regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

This could have been avoided if:

Options:

A.

the project team documented customer requests and obtained sign-off.


B.

a change control process for requirements and their statuses was followed.


C.

the project manager circulated the meeting minutes after the discussions with all the attendees.


D.

the customer met with regulatory authorities to verify that their requirements were also considered.


Expert Solution
Questions # 38:

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

Options:

A.

Decomposition model


B.

Context diagram


C.

Swimlane diagram


D.

Business analysis work plan


Expert Solution
Questions # 39:

A project team has been assembled to reduce production costs. The business analyst is working with the project team to review and approve requirements. A stakeholder from the assembly line area has an issue with one of the requirements since it is dependent on using existing equipment that is set to be retired within the next six months.

Which of these techniques would the business analyst use to manage issues identified by stakeholders with requirements to ensure that

those issues are resolved?

Options:

A.

A Interviews


B.

Process modeling


C.

Estimation


D.

Problem tracking


Expert Solution
Questions # 40:

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

Options:

A.

Risks identified in the risk management plan were not addressed properly.


B.

There is no issue since the product exceeded the customer expectations.


C.

The sponsor approved the release of the product without reviewing the budget.


D.

Requirements were not properly traced and monitored.


Expert Solution
Viewing page 4 out of 6 pages