PMI Professional in Business Analysis PMI-PBA Question # 35 Topic 4 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 35 Topic 4 Discussion

PMI-PBA Exam Topic 4 Question 35 Discussion:
Question #: 35
Topic #: 4

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?


A.

How requirement changes will impact the requirements baseline


B.

How requirement changes will be implemented


C.

How requirement changes will impact the validation plan


D.

How requirement changes will be communicated


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.