PMI Professional in Business Analysis PMI-PBA Question # 40 Topic 5 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 40 Topic 5 Discussion

PMI-PBA Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?


A.

Risks identified in the risk management plan were not addressed properly.


B.

There is no issue since the product exceeded the customer expectations.


C.

The sponsor approved the release of the product without reviewing the budget.


D.

Requirements were not properly traced and monitored.


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.