PMI Professional in Business Analysis PMI-PBA Question # 40 Topic 5 Discussion
PMI-PBA Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5
A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?
A.
Risks identified in the risk management plan were not addressed properly.
B.
There is no issue since the product exceeded the customer expectations.
C.
The sponsor approved the release of the product without reviewing the budget.
D.
Requirements were not properly traced and monitored.
According to the PMI Professional in Business Analysis (PMI-PBA)® Examination Content Outline, one of the tasks under the domain of Planning is to “Develop a risk management plan for business analysis activities and monitor risks, issues, and assumptions” (Task 9). This implies that the business analyst is responsible for identifying, analyzing, and managing the risks that may affect the business analysis activities and deliverables. If the risks are not addressed properly, they may result in deviations from the baseline budget, schedule, scope, or quality of the product. Therefore, the issue in this scenario could be that the risks identified in the risk management plan were not addressed properly.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit