Question #: 37
Topic #: 4

A project that was going well for the last few months has encountered a situation—regulatory authorities have deemed that the project does not meet their requirements. Although regulatory requirements were identified during an earlier phase of the project, there is no substantial evidence to prove that the requirements were formally rejected.

This could have been avoided if:


A.

the project team documented customer requests and obtained sign-off.


B.

a change control process for requirements and their statuses was followed.


C.

the project manager circulated the meeting minutes after the discussions with all the attendees.


D.

the customer met with regulatory authorities to verify that their requirements were also considered.