Questions # 51:

Which of the following best describes the function of the requirements baseline?

Options:

A.

Controls the product development and evolution.


B.

Provides the basis for the development scope.


C.

Tracks the progress of requirements documentation.


D.

Defines how the project will be scheduled.


Expert Solution
Questions # 52:

What should a business analyst do after discovering that two solution requirements conflict?

Options:

A.

Consult the sponsor(s) and log the constraint.


B.

Perform an impact analysis and propose a lower-cost alternative.


C.

Update the requirements baseline and upload it to the project repository.


D.

Communicate the conflict to stakeholders and facilitate a resolution.


Expert Solution
Questions # 53:

A firm implements SharePoint and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain activities. The SharePoint team needs to know which activities should trigger the notification workflow.

Which workflow trigger should the business analyst incorporate?

Options:

A.

Any change to the requirements matrix


B.

Changes to test cases traced to requirements


C.

Change through project life cycle


D.

Changes to stakeholder memberships


Expert Solution
Questions # 54:

While preparing a business case, an experienced business analyst faces difficulty in deciding which of three different solution options to recommend. The senior vice president (SVP) who requested the business case favors an outsourced solution; however, an analysis

favors a custom-developed solution, either built internally or using contract labor.

To prepare the recommendation, what should the business analyst do?

Options:

A.

Perform solution evaluation.


B.

Formulate a weighted-ranking matrix.


C.

Review the stakeholder analysis.


D.

Recommend the SVP's choice, as it is most likely to be adopted.


Expert Solution
Questions # 55:

A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.

What should the business analyst do to obtain signoff?

Options:

A.

Contact the sponsor.


B.

Contact the stakeholder who provided the majority of requirements in the traceability matrix.


C.

No signoff is necessary.


D.

Refer to the RACI matrix to identify who is responsible for signoff.


Expert Solution
Questions # 56:

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?

Options:

A.

Requirements cards


B.

Requirements baseline


C.

Requirements management tool


D.

Requirements traceability matrix


Expert Solution
Questions # 57:

A key component of the business analyst's role during acceptance testing is to:

Options:

A.

execute all acceptance tests on behalf of the user community.


B.

delegate execution of acceptance testing and defect identification to users.


C.

act as a resource only when users encounter difficulties while performing tests.


D.

assist the quality assurance department by defining acceptance criteria.


Expert Solution
Questions # 58:

How can a SWOT analysis help when deciding between several possible options to address a business problem?

Options:

A.

It can help the product owner to determine opportunity cost of not choosing an option.


B.

It can help the stakeholders to determine how to avoid the threats of each option.


C.

It can help the project sponsor to determine the valuation of each option.


D.

It can help the stakeholders identify the strengths and weaknesses of each option.


Expert Solution
Questions # 59:

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?

Options:

A.

Ask the project sponsor to prioritize the requirements.


B.

Organize a new elicitation workshop.


C.

Perform a Pareto analysis on the requirements.


D.

Validate the requirements before continuing with development.


Expert Solution
Questions # 60:

Change control systems include provisions to implement changes without formal review in the event of an emergency. When this provision is utilized:

Options:

A.

the risk associated with the change is not evaluated.


B.

changes must still be documented and captured.


C.

a change control board should be established.


D.

changes can be applied without further managerial involvement.


Expert Solution