The requirements baseline is a set of approved and prioritized requirements that are used as the basis for the development scope. The requirements baseline defines what the project or program will deliver and what the stakeholders expect to receive. The requirements baseline also serves as a reference point for managing changes and measuring progress. References: PMI Guide to Business Analysis, Chapter 9, Section 9.3.1; PMI Professional in Business Analysis (PMI-PBA)® Examination Content Outline, Domain IV: Traceability and Monitoring, Task 1.