PMI Professional in Business Analysis PMI-PBA Question # 52 Topic 6 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 52 Topic 6 Discussion

PMI-PBA Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

What should a business analyst do after discovering that two solution requirements conflict?


A.

Consult the sponsor(s) and log the constraint.


B.

Perform an impact analysis and propose a lower-cost alternative.


C.

Update the requirements baseline and upload it to the project repository.


D.

Communicate the conflict to stakeholders and facilitate a resolution.


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.