PMI Professional in Business Analysis PMI-PBA Question # 59 Topic 6 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 59 Topic 6 Discussion

PMI-PBA Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

The project team is early in the development phase of a new product. The project will need to be completed on a tight timeline and with a lean budget.

What should the team do to reduce the risk of rework?


A.

Ask the project sponsor to prioritize the requirements.


B.

Organize a new elicitation workshop.


C.

Perform a Pareto analysis on the requirements.


D.

Validate the requirements before continuing with development.


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.