New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Professional in Business Analysis PMI-PBA Question # 56 Topic 6 Discussion

PMI Professional in Business Analysis PMI-PBA Question # 56 Topic 6 Discussion

PMI-PBA Exam Topic 6 Question 56 Discussion:
Question #: 56
Topic #: 6

During the project execution phase, the client requests the addition of a new feature. Which of the following would allow the business analyst to determine the impact for the specific requirement change?


A.

Requirements cards


B.

Requirements baseline


C.

Requirements management tool


D.

Requirements traceability matrix


Get Premium PMI-PBA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.