Questions # 31:

You are the project manager of a project .You have just completed the Define Activities, activity resources estimating, and Estimate Activity Durations processes. Which process have you left out?

Options:

A.

Control Schedule


B.

Create WBS


C.

Sequence Activities


D.

Operations


Expert Solution
Questions # 32:

You have a piece of equipment that was purchased for your project recently for $5,000 and is expected to last 5 years in production. At the end of the five years, the expected worth of the equipment is $2,000. Using the straight-line deprecation, what is the amount that can be written off each year?

Options:

A.

$600


B.

$1200


C.

$3000


D.

$100


Expert Solution
Questions # 33:

A major assumption of all network scheduling methods is that the activity duration must be _____.

Options:

A.

Statistically dependent


B.

Variance distributed


C.

Statistically independent


D.

Deterministic


Expert Solution
Questions # 34:

The planning processes are:

Options:

A.

Define Scope, Resource planning, Estimate Costs, Schedule development. Define Activities


B.

Inputs, Control, Status reports, Risk management


C.

Planning, Resource planning, Quality assurance, Risk control


D.

Define Scope, Team development, Control Schedule, Budget control, Contract administration


Expert Solution
Questions # 35:

A Reserve Analysis is a technique for:

Options:

A.

Estimate Activity Durations


B.

Estimate Activity Resources


C.

Sequence Activities


D.

Define Activities


Expert Solution
Questions # 36:

Which is not the tools and techniques used in Contract Administration:

Options:

A.

Contract change control system


B.

Contract negotiation


C.

Payment system


D.

Performance rating


Expert Solution
Questions # 37:

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

Options:

A.

Start-to-Finish


B.

Finish-to-Start


C.

Start-to-Start


D.

Finish-to-Finish


Expert Solution
Questions # 38:

Purchasing insurance is an example of __________.

Options:

A.

Transfer


B.

Acceptances


C.

Mitigation


D.

Contingency


Expert Solution
Questions # 39:

Which of the following is an output of Define Scope?

Options:

A.

PBS


B.

Project Scope statement


C.

WBS Template


D.

Constraints


Expert Solution
Questions # 40:

Market conditions are a part of ________.

Options:

A.

Enterprise environmental factors


B.

Project management concerns


C.

Organizational process assets


D.

Cost factor


Expert Solution
Questions # 41:

In which type of organization, a project manager is in complete control of the project?

Options:

A.

Projectized organization


B.

Balanced Matrix organization


C.

Strong Matrix


D.

Weak Matrix organization


Expert Solution
Questions # 42:

In which type of organization, a project manager is in complete control of the project?

Options:

A.

Projectized organization


B.

Balanced Matrix organization


C.

Strong Matrix


D.

Weak Matrix organization


Expert Solution
Questions # 43:

Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?

Options:

A.

Precedence Diagramming Method (PDM)


B.

Gantt Cnart Diagram (GCD)


C.

Dependency Diagramming Method (DDM)


D.

Arrow Diagramming Method (ADM)


Expert Solution
Questions # 44:

A _______ is a series of actions bringing about a result.

Options:

A.

Project plan


B.

Process


C.

Schedule


D.

Flowchart


Expert Solution
Questions # 45:

Project scope is:

Options:

A.

The work that must be done in order to deliver a product with the specified features and functions.


B.

The features and functions that are to be included in a product or service.


C.

A narrative description of work to be performed under contract.


D.

a and b


Expert Solution