Pass the PMI CAPM CA0-001 Questions and answers with CertsForce

Viewing page 2 out of 11 pages
Viewing questions 16-30 out of questions
Questions # 16:

Which of the following best describes project scope?

Options:

A.

The work that must be done in order to deliver a product with the specified features and functions


B.

The description of the project deliverables


C.

The authorizing document that allows the project manager to move forward with the project and to assign resources to the tasks


D.

The process of planning and executing all of the required work to deliver the project


Expert Solution
Questions # 17:

In PMBOK, the buyer is ________ to the project team.

Options:

A.

Internal


B.

External


C.

Outside


D.

Assigned


Expert Solution
Questions # 18:

Another term for top down estimating is:.

Options:

A.

Analogous estimating


B.

Life-cycle costing


C.

Parametric modeling


D.

Bottom up estimating


Expert Solution
Questions # 19:

Define Scope involves subdividing the major project deliverables into smaller, more manageable components to __________.

Options:

A.

Improve the accuracy of cost, time and resource estimates


B.

Define a baseline for performance measurement and control


C.

Facilitate clear responsibility assignments


D.

Al1 of the above


Expert Solution
Questions # 20:

Which process group is for detailed resource assignments and responsibilities?

Options:

A.

Human resources management plan


B.

Project charter


C.

Aplan


D.

Project management plan


Expert Solution
Questions # 21:

Which of the following is ensuring that all features and functions are included in a product or service

Options:

A.

Project scope


B.

Project verification


C.

Project control


D.

Product scope


Expert Solution
Questions # 22:

Which of the following is NOT an example of a type of schedule report?

Options:

A.

Gantt chart


B.

Milestone chart


C.

fishbone diagram


D.

network diagram


Expert Solution
Questions # 23:

Which type of network diagram allows you to depict four types of dependencies (finish-to-start, finish-to-finish, start-to-start, and start-to-finish)?

Options:

A.

Precedence Diagramming Method (PDM)


B.

Gant Cnart Diagram (GCD)


C.

Dependency Diagramming Method (DDM)


D.

Arrow Diagramming Method (ADM)


Expert Solution
Questions # 24:

Which is not included in Performance improvements :

Options:

A.

Improvements in amount of overtime worked


B.

Improvements in individual skills


C.

Improvements in team behaviours


D.

Improvements in team capabilities


Expert Solution
Questions # 25:

Which process must occur after a project manager has been assigned to the project?

Options:

A.

Collect Requirements


B.

Develop the project charter


C.

Develop the project statement of work


D.

Develop project closing document


Expert Solution
Questions # 26:

Which of the following is not a part of the Earned Value calculations?

Options:

A.

Unknown Unknowns


B.

Project Budget


C.

Known Unknowns


D.

Amount of work completed


Expert Solution
Questions # 27:

Which of the following is a common characteristic of most project life cycle descriptions?

Options:

A.

Cost and staffing are low at the start, higher towards the end. and drop rapidly as the project nears completion.


B.

The probability of successfully completing the project is highest at the start of the project.


C.

Stakeholders have the most influence on the final characteristics of the product at the end of the project.


D.

a and b


Expert Solution
Questions # 28:

Which is the most risky phase of a project?

Options:

A.

Planning


B.

Closing


C.

Execution


D.

Control


Expert Solution
Questions # 29:

A process that is not part of a Project Risk Management is:

Options:

A.

Identification


B.

Solicitation


C.

Quantification


D.

Response Development


Expert Solution
Questions # 30:

Which of the following is NOT input of Identify Risks?

Options:

A.

Project Charter


B.

Stakeholder Register


C.

Pis'* Management Plan


D.

Activity Cost Estimates


Expert Solution
Viewing page 2 out of 11 pages
Viewing questions 16-30 out of questions