Questions # 46:

A Trend Analysis is best described as:

Options:

A.

Examining project performance over time


B.

Calculating Earned Value


C.

Calculating Cost Variance


D.

Analyzing performance of similar projects over time


Expert Solution
Questions # 47:

You are the project manager and you have created a contract for your customer. The contract must have ________.

Options:

A.

Offer and consideration


B.

Start date and acceptance of start date


C.

Signatures and the stamp of a notary public


D.

Signatures of all stakeholders


Expert Solution
Questions # 48:

A Project Scope Management includes :

Options:

A.

Initiation


B.

Project Plan Execution


C.

Overall Change Control


D.

Report Performance


Expert Solution
Questions # 49:

Analogous Estimate Costs is _________.

Options:

A.

Generally Accurate


B.

Generally less accurate


C.

Bottom-up estimating


D.

None


Expert Solution
Questions # 50:

The project management plan:

Options:

A.

Identifies all the steps and processes that will be used after a project is initiated


B.

Steps needed to complete a project task


C.

Prepared at the beginning and fixed throughout the execution of the project


D.

Includes project charter


Expert Solution
Questions # 51:

When the version control numbers should change?

Options:

A.

Any change occurs


B.

Major changes are made


C.

Any change related to scope only


D.

Only if minor changes are made


Expert Solution
Questions # 52:

Which of the following is an output of a Verify Scope process?

Options:

A.

Formal acceptance


B.

WBStemplate


C.

SOW acceptance


D.

Rework


Expert Solution
Questions # 53:

Information should be communicated to __________.

Options:

A.

Everyone in the communication plan


B.

Everyone on the team


C.

Sponsor


D.

Team 'eacl


Expert Solution
Questions # 54:

Create Procurement document is done in _______.

Options:

A.

Plan Procurements


B.

Conduct Procurements


C.

Administer Procurements


D.

Close Procurements


Expert Solution
Questions # 55:

Acceptance of the product should be ________.

Options:

A.

Formal


B.

Consistent


C.

Personal


D.

Verbal


Expert Solution
Questions # 56:

A Risk Register is a part of the ________.

Options:

A.

Project Scope Statement


B.

Project Management plan


C.

Project Scheduling plan


D.

Project Charter


Expert Solution
Questions # 57:

ISO Stands for __________.

Options:

A.

International Organization for Standardization


B.

International Standardized Organization


C.

'n Standardized Organization


D.

Indiana Standardized Organization


Expert Solution
Questions # 58:

You are the project manager of a project. If there are approved changes to the original scope, what you do with the old original scope?

Options:

A.

Save the old versions


B.

No need to save old version


C.

Scrap the old version


D.

Old version is not required


Expert Solution
Questions # 59:

The end of the project comes after which of the following?

Options:

A.

Project charter


B.

Final deliverable


C.

Schedule


D.

QA activities are done


Expert Solution
Questions # 60:

Which of the following does not provided by scope statement?

Options:

A.

Project justification


B.

Project product


C.

Project manager authority


D.

Project objective


Expert Solution