PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 50 Topic 6 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 50 Topic 6 Discussion

CA0-001 Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

The project management plan:


A.

Identifies all the steps and processes that will be used after a project is initiated


B.

Steps needed to complete a project task


C.

Prepared at the beginning and fixed throughout the execution of the project


D.

Includes project charter


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.