You are the project manager for the software Project. This project must be completed within one year. This is an example of which of the following?

Options:

A.

Schedule


B.

Assumption


C.

Constraint


D.

Planning process


Expert Solution
Questions # 2:

A scope management plan In which of the following scope management processes is the scope management plan prepared?

Options:

A.

Initiation


B.

Collect Requirements


C.

Define Scope


D.

Verify Scope


Expert Solution
Questions # 3:

At which stage, stakeholders have the maximum influence on a project?

Options:

A.

Initial stage


B.

Closing stage


C.

Execution stage


D.

None of the above


Expert Solution
Questions # 4:

What are common types of cost-reimbursable contracts?

Options:

A.

CPF


B.

CPFF


C.

CPIF


D.

Al1 of the above


Expert Solution
Questions # 5:

The activity that is most concerned with the current status of the project schedule is called ___________.

Options:

A.

Project time management


B.

Control Schedule


C.

Monitoring and controlling


D.

Al1 of the above


Expert Solution
Questions # 6:

The primary output of the project closing process ____________.

Options:

A.

To formalize and distribute all information pertaining to the project closing


B.

Lessons learned


C.

To get customer and sponsor approval


D.

Milestone list


Expert Solution
Questions # 7:

What is the purpose of the WBS?

Options:

A.

To show which work elements have been assigned to organizational units.


B.

To ensure that all work within a project is identified and defined within a common framework.


C.

To show the organizational structure of a program.


D.

all of the above


Expert Solution
Questions # 8:

Your project has a budget of $240,000 and is expect to last for 1 year, with the work and budget spread evenly across all months. The project is now in the fourth month, the work is on schedule, but you have spent $120,000 of the project budget. What is your COST Variance percentage in this case?

Options:

A.

-50%


B.

50%


C.

40%


D.

20%


Expert Solution
Questions # 9:

Which document formally authorizes a project?

Options:

A.

The project charter


B.

Project scope statement


C.

The P'oject contract


D.

Project closing document


Expert Solution
Questions # 10:

Which of the following is not a tool or technique for a Source Selection?

Options:

A.

Contract negotiation


B.

Weighting system


C.

Payment system


D.

Screening system


Expert Solution
Questions # 11:

A Project Cost Management plan is created as a part of:

Options:

A.

Develop Project Management Plan process


B.

Control Costs process


C.

Determine Budget process


D.

Estimate Costs process


Expert Solution
Questions # 12:

To calculate the late start and late finish dates for a set of tasks , you must do :

Options:

A.

An analysis of the critical path


B.

A forwards pass


C.

A backwards pass


D.

a and g


Expert Solution
Questions # 13:

Conformance to specifications document is one description of _________.

Options:

A.

Quality


B.

Scope


C.

Integration


D.

Procurement


Expert Solution
Questions # 14:

If you are project manager for a Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project?

Options:

A.

Historical information


B.

WBS


C.

Business plans


D.

RBS


Expert Solution
Questions # 15:

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively. The mean is _____.

Options:

A.

30.0


B.

22.5


C.

25.0


D.

27.5