PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 12 Topic 2 Discussion

PMI Certified Associate in Project Management (CAPM) Certification CA0-001 Question # 12 Topic 2 Discussion

CA0-001 Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

To calculate the late start and late finish dates for a set of tasks , you must do :


A.

An analysis of the critical path


B.

A forwards pass


C.

A backwards pass


D.

a and g


Get Premium CA0-001 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.