CA0-001 Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

A Project Cost Management plan is created as a part of:


A.

Develop Project Management Plan process


B.

Control Costs process


C.

Determine Budget process


D.

Estimate Costs process