Questions # 61:

Based on the PMBOK, who is ultimately responsible for the project quality?

Options:

A.

Project team


B.

Project manager


C.

QA manager


D.

Validation engineer


Expert Solution
Questions # 62:

You are the project manager of the MKTG Project. The project has a budget of $200,000 and is expected to last 2 years. The project is now 20 percent complete and is on schedule. What is the BAC?

Options:

A.

$-00,000


B.

$200,00


C.

$50,000


D.

None of the above


Expert Solution
Questions # 63:

______________ provides details about how the project scope may be changed.

Options:

A.

Control Scope system


B.

VeiirV Scope


C.

Scope Charter


D.

Scope Management plan


Expert Solution
Questions # 64:

Project just went into inclusion mode. This means that project __________.

Options:

A.

Has become part of the business processes


B.

Has been accepted by the sponsor and the client


C.

Will be closed due to lack of resources


D.

None of the above


Expert Solution
Questions # 65:

A contract cannot contain _____________.

Options:

A.

Illegal activities


B.

deadline for the completion of the work


C.

Penalties and fines for disclosure of intellectual rights


D.

Al1 of the above


Expert Solution
Questions # 66:

At what point in a project do you have the highest probability that it will fail?

Options:

A.

The beginning of the project


B.

^ust before the end of the project


C.

QA Phase


D.

Execution phase


Expert Solution
Questions # 67:

_________ is the international organization that controls the standards for quality.

Options:

A.

ISO


B.

CAPM


C.

PMI


D.

iscn


Expert Solution
Questions # 68:

_______ is the road map for the execution of the project.

Options:

A.

Project plan


B.

sow


C.

WBS


D.

Strategic planning


Expert Solution
Questions # 69:

Which of the following are input of close project process?

Options:

A.

Project management plan


B.

Contract documentation


C.

Deliverables


D.

All of the above


Expert Solution
Questions # 70:

What is a corrective action?

Options:

A.

An action that brings future project events Into alignment with the project plan


B.

An action to correct something in the project


C.

An action to prevent something in the project


D.

Corrective action is not related to project


Expert Solution
Questions # 71:

Which one of the following comes first in the project plan?

Options:

A.

Scope Statement


B.

Quality Plan


C.

WBS


D.

Development Plan


Expert Solution
Questions # 72:

In which phase project manager is assigned to a project?

Options:

A.

During the initiation stage


B.

During the planning stage


C.

After approval of budget


D.

After the project is proven feasible


Expert Solution
Questions # 73:

Which time estimating tools estimate the basis for activity durations can be quantitatively determined by multiplying the quantity of work to be performed by the productivity rate?

Options:

A.

Parametric estimating


B.

Funding limit reconciliation


C.

Reserves analysis


D.

None of the above


Expert Solution
Questions # 74:

A complete set of indexed project records is called __________.

Options:

A.

Project archives


B.

Index


C.

sow


D.

Project History


Expert Solution
Questions # 75:

Who is responsibility for making sure that a message in the project team is understood

Options:

A.

Project Manager


B.

Sender


C.

Project coordinator


D.

Sponsor


Expert Solution